Mpumalanga’s R2.8 Billion Mega Hospital Under the Spotlight

Written on November 18, 2026
Gideon Muteb


The new Mapulaneng Regional Hospital construction site during an oversight visit by Parliament’s Portfolio Committee on Public Works and Infrastructure on 3 February 2026. Photo: Mpumalanga Department of Public Works, Roads and Transport.

The new Mapulaneng Regional Hospital in Bushbuckridge has come under renewed public scrutiny following allegations of ongoing vandalism and theft at the construction site. The claims surfaced as contractors prepared to resume work on the long-delayed hospital.

The Mpumalanga provincial government announced the 365-bed hospital costing R2.8 billion in March 2017 to replace the original Masana Hospital, which was built in 1936 and later renamed Mapulaneng Hospital. The new facility was planned as a regional referral hospital for Bushbuckridge and surrounding communities.



The project missed its July 2026 completion deadline due to the liquidation of the Phase 3A contractor and prolonged community-related disruptions. The resulting site closure prevented work on phases 3A and 3C.

In mid-October, the province introduced a new contractor for Phase 3A, which includes hospital wards, operating theatres and radiology facilities. A revised completion date was still pending.

As preparations to resume construction moved ahead, a local news outlet alleged in a Facebook post that electrical cables, air-conditioning systems, lighting equipment, aluminium windows and doors were being stolen from the site. The post also raised allegations of corruption and mismanagement in connection with the project.



Responding on 17 November, the Mpumalanga Department of Public Works, Roads and Transport said the incidents cited in the post took place in May and June 2026, while the site was closed following the liquidation of the original contractor. The department said it had submitted the cost of the stolen items to the liquidator for recovery.

The department said it tightened security across the site in July and had received no reports of further theft since the security provider took full responsibility that month. It said the post provided no evidence linking the incidents to project delays, corruption or mismanagement. It called on the outlet to retract the post and issue a correction, and said it was open to an organised site visit so security conditions could be independently verified.

The department said contractors for phases 3A and 3C were preparing to return to the site. Its November statement gave no revised date for completing the work or handing over the hospital to serve communities in the Bohlabela District.